Skandagiri Progress ← Back to Dashboard
Works Kanban · July 2026

What's done, what's moving, what's next.

All infrastructure and maintenance works mapped across three stages.

click any card to expand subtasks

Not Started 9
🚿

Exit Valve — Fresh Water Connections

WaterCategory 1📞 Niranjan EE
▶ 2 tasks
  • ○Install exit valve for 13th & 14th floor extension
  • ○Install exit valve for all fresh water connections
🧹

Solid Waste Converter

Category 1👤 Person TBD📞 Gunashekhar (Hombale)
▶ 1 task
  • ○Assign 1 person for solid waste converter
🚪

Locking Shaft & Missing Doors

CivilHombale📞 Gunashekhar (Hombale)
▶ 2 tasks
  • ◑List of locking shaft & missing doors being compiled from members
  • ○Gunashekhar (Hombale) to rectify broken/missing doors
🪨

Entry & Exit Slab Replacement

Civil⚠ Stalled📞 Gunashekhar (Hombale)
▶ 3 tasks
  • ○Following up with Gunashekhar sir (Hombale) for months — no visible update yet
  • ○Material procurement
  • ○Slab replacement work
📊

Borewell Yield Report

Water📞 Vinayak (Hombale)
▶ 2 tasks
  • ○Contact Vinayak (Hombale) for yield data
  • ○Review and document yield report
💚

Waste Segregation & Composting

BDAHombale📞 Inbavalli AEE📞 Gunashekhar (Hombale)
▶ 5 tasks
  • ○Inbavalli AEE to provide per-block wet and dry waste bins
  • ○Install dry & wet waste bins across campus (Commissioner's proposal)
  • ○Inbavalli AEE to issue work order to Hombale for dedicated STP person
  • ○Inbavalli AEE to issue work order to Hombale for organic waste converter machine
  • ○Process wet waste through composting unit
💧

Basement Seepage

CivilBDACategory 1📞 Gunashekhar (Hombale)
▶ 2 tasks
  • ○Seal expansion joints opened by contractor during basement cleaning
  • ○Resolve ongoing water seepage in basement
🔋

DG Maintenance & Backup DG

Electrical⚠ Critical📞 Niranjan EE
▶ 2 tasks
  • ○Schedule and carry out DG maintenance
  • ○Arrange backup DG — critical during power failure
🔧

Transformer Maintenance

ElectricalBDA📞 Niranjan EE
▶ 2 tasks
  • ○Inspect transformers — power fluctuations reported in some flats
  • ○Address maintenance issues found
In Progress 19
🌧️

Rainwater Harvesting (RWH)

WaterBDACategory 1📞 Inbavalli AEE📞 Gunashekhar (Hombale)
▶ 9 tasks
  • ✓3 rainwater percolation pits unearthed using JCB from Hombale (8 Aug 2026)
  • ✓Park-area pits surveyed — all located except 3 (16 Aug 2026 · Hombale survey team)
  • ✓RWH survey maps received (16 Aug 2026)
  • ✓Coordinated with NGO that constructed the pits (16 Aug 2026)
  • ◑NGO heightening pits to current level using rings — target Wed 19 Aug 2026
  • ○Locate remaining 3 percolation pits in park area
  • ○Clean all rainwater harvesting tanks
  • ○Install motor/pump for RWH system
  • ○Connect percolation pits to RWH system
⚡

Earth Pits Maintenance

Electrical📞 Inbavalli AEE & Gunashekhar
▶ 3 tasks
  • ✓18 earth pits recovered
  • ◑8 more earth pits to go
  • ✓JCB from Hombale deployed — also used to unearth 3 percolation pits
🧯

Fire Safety & Extinguisher Refill

Category 1⚠ Expires end of month📞 Inbavalli AEE
▶ 3 tasks
  • ○Fire extinguisher refill — expiring end of month, urgent
  • ○Fire alarm systems & fire safety equipment — pending
  • ○Inbavalli AEE to follow up
💦

Cauvery Water Connection

WaterBDACategory 1📞 Inbavalli AEE📞 Naveen AEE (BWSSB)🏆 Milestone
▶ 7 tasks
  • ✓Formal request submitted by BDA to BWSSB (Dec 2025)
  • ✓BWSSB agreed in principle — will issue demand note to BDA
  • ✓EE Inbavalli & AEE Naveen visited Phase 2 (8 Aug 2026)
  • ✓BDA confirmed will bear all expenses for all 3 phases
  • ○Larger-diameter BWSSB pipeline from Safal Market side
  • ○Demand note to be issued by BWSSB → BDA to process
  • ⏱BWSSB estimated timeline: 6 months to 1 year for completion
📄

KSPCB Consent Renewal

BDA📞 Inbavalli AEE
▶ 1 task
  • ◑Show-cause notice — renewal in progress (Inbavalli AEE)
⚠️

STP Overhead Tank — Discolored Water

WaterCategory 1⚠ Health hazard📞 Inbavalli AEE📞 Niranjan EE📞 Gunashekhar (Hombale)
▶ 2 tasks
  • ○Complete motor installation with auto-controller to resolve discoloration
  • ○Hombale to assign dedicated STP maintenance person
🛑

Speed Breakers

CivilBDA📞 Niranjan EE
▶ 4 tasks
  • ✓Locations and specs finalized
  • ✓Speed breaker materials received (14 Aug 2026)
  • ✓Stilt — speed breaker installation completed (21 Aug 2026)
  • ○Basement — speed breaker installation still pending
💧

Existing Borewells — 3 of 4 Failed

WaterCategory 1⚠ 3 failed📞 Inbavalli AEE📞 Gunashekhar (Hombale)
▶ 4 tasks
  • ✓1 existing borewell — motor repair completed, operational
  • ✕Borewell near A block — failed, will not be restored
  • ✕Borewell near B block — failed, will not be restored
  • ✕Borewell in Labour Colony — failed, will not be restored
💧

New Borewells — 5 Drilled (2 Fitted, 2 Pending, 1 Failed)

WaterCategory 1📞 Inbavalli AEE📞 Gunashekhar (Hombale)
▶ 4 tasks
  • ✓2 new borewells — motors fitted, operational
  • ◑2 new borewells — motors yet to be fitted
  • ✕1 new borewell failed — no water found
  • ○Yield reports pending for all new borewells
⚙️

Fresh Water & STP Motors

WaterMaintenance📞 Niranjan EE📞 Gunashekhar (Hombale)
▶ 7 tasks
  • ✓14 new motors received in 2 batches
  • ✓7 Fresh Water motors — installed with starters
  • ✓7 STP motors — installed
  • ◑7 STP motor starters — scheduled Mon 17 Aug 2026
  • ○Contact automatic water controller team to verify post motor installation
  • ○Old 14 motors to STP building as backup
  • ✓Coordination by Gunashekar Sir (Hombale) & BDA team
🤖

Water Automation Controller

WaterElectrical📞 Niranjan EE
▶ 4 tasks
  • ◑Fresh water controller — installation in progress
  • ○Contact automatic water controller team to verify post motor installation
  • ✓STP controller integrated
  • ✓Generator made automatic
🔧

Plumbing & Blockages

WaterCivilCategory 1📞 Niranjan EE
▶ 4 tasks
  • ◑Flat-by-flat checks — 70+ flats ongoing
  • ◑External pipe access planning
  • ✓Y-strainer installation — done for all 6 blocks (8×2.5" + 4×2" per block, 72 total)
  • ○Silt accumulation in pipes — ground sump filtration needed
⚡

Electrical Rectification

Electrical📞 Niranjan EE
▶ 8 tasks
  • ✓E Block ATS — rectified by BESCOM & AXON
  • ✓D Block ATS — rectified by BESCOM & AXON
  • ✓MCB electrical issues in A, D & E Blocks — rectified
  • ○3 street lights in front of B & C blocks — not working
  • ○Street lights towards F block and road — not working
  • ○Street lights near transformer — not working
  • ○Parking street lights — not working
  • ○Street lights towards back wall — not working
🏗️

Civil Works

Civil📞 Inbavalli AEE📞 Niranjan EE📞 Bhuvaneshwar EE📞 Jayaraj RCCL📞 Gunashekhar (Hombale)
▶ 8 tasks
  • ◑Dust mound clearance — starts Mon 17 Aug, ~10 days (Bhuvaneshwar EE & RCCL DGM · target Wed 26 Aug)
  • ◑Wall behind sump & STP — level with sand to stop water logging
  • ◑Back wall — closed on transformer side with temporary sheets (not a permanent fix)
  • ✓Back wall near STP — sped up, significant progress made
  • ◑Back wall work started near F block
  • ○Inbavalli AEE & Niranjan EE to discuss with RCCL & Hombale for permanent resolution
  • ✓Debris cleared
  • ○Slab replacement — not started yet
🌳

Park Work

CivilStarted Jul 16📞 Niranjan EE
▶ 5 tasks
  • ◑Pavement laying — ongoing
  • ◑Landscaping & debris removal — ongoing
  • ◑Jogging track construction — commenced
  • ◑Children's play area & walking track with gazebo — in progress, to be fenced
  • ○Remaining park works
🛡️

Security & CCTV

Security📞 Inbavalli AEE
▶ 6 tasks
  • ✓Blind spots identified
  • ✓5 CCTV cameras installed
  • ✓CCTV recording operational (NVR / HDD issue resolved)
  • ✓Parking data consolidated
  • ○Boom barrier — requested for vehicle entry tracking
  • ○Parking allotment/numbering — flagged for discussion with BDA
💧

Water Complaints Resolution

WaterCategory 1📞 Inbavalli AEE
▶ 3 tasks
  • ✓161 flats tracked block-wise (A–F)
  • ◑Plumbing team working through list
  • ◑Staging-required flats being scheduled
📋

FMS & AMC

Maintenance📞 Niranjan EE📞 Niranjan EE
▶ 4 tasks
  • ✓FMS EOI for empanelment submitted
  • ○Follow up with Niranjan EEAfter Aug 22
  • ○Motor AMC proposal
  • ○Define SOPs and accountability
Done 6
🤖

STP Controller & Generator Automation

ElectricalWater📞 Niranjan EE
▶ 2 tasks
  • ✓STP automation controller integrated
  • ✓Generator made fully automatic
♻️

STP Cleaning

WaterMaintenanceCategory 1👤 Person TBD📞 Gunashekhar (Hombale)
▶ 4 tasks
  • ✓Sludge cleared
  • ✓System cleaning completed
  • ✓Motor servicing coordinated
  • ○Assign 1 person for ongoing STP monitoring
🛗

Lift Maintenance

Maintenance📞 Niranjan EE
▶ 7 tasks
  • ✓Quarterly lift maintenance (6 July 2026) — done
  • ✓B Block — 2 lifts done (passenger + service)
  • ✓C Block — 2 lifts done (passenger + service)
  • ✓D Block — 2 lifts done (passenger + service)
  • ✓E Block — 2 lifts done (passenger + service)
  • ✓F Block — 2 lifts done (passenger + service)
  • ○A Block — 2 lifts pending (passenger + service)
🧹

Basement & Stilt Cleaning

Civil📞 Gunashekhar (Hombale)
▶ 3 tasks
  • ✓Basement cleaned
  • ✓Stilt areas cleaned
  • ✓Exit ramp blockage cleared
📱

MyGate & Documentation

Management
▶ 3 tasks
  • ✓Vendor directory added
  • ✓Parking data consolidated
  • ✓Block SPOCs and issue tracking set up
📋

FMS EOI Submitted

Maintenance📞 Niranjan EE
▶ 1 task
  • ✓Expression of Interest for FMS empanelment submitted