Skandagiri Progress ← Back to Dashboard
Works Kanban · July 2026

What's done, what's moving, what's next.

All infrastructure and maintenance works mapped across three stages.

click any card to expand subtasks

Not Started 9
🚿

Exit Valve — Fresh Water Connections

WaterCategory 1📞 Niranjan EE
2 tasks
  • Install exit valve for 13th & 14th floor extension
  • Install exit valve for all fresh water connections
🧹

Solid Waste Converter

Category 1👤 Person TBD📞 Gunashekhar (Hombale)
1 task
  • Assign 1 person for solid waste converter
🚪

Locking Shaft & Missing Doors

CivilHombale📞 Gunashekhar (Hombale)
2 tasks
  • List of locking shaft & missing doors being compiled from members
  • Gunashekhar (Hombale) to rectify broken/missing doors
🪨

Entry & Exit Slab Replacement

Civil⚠ Stalled📞 Gunashekhar (Hombale)
3 tasks
  • Following up with Gunashekhar sir (Hombale) for months — no visible update yet
  • Material procurement
  • Slab replacement work
📊

Borewell Yield Report

Water📞 Vinayak (Hombale)
2 tasks
  • Contact Vinayak (Hombale) for yield data
  • Review and document yield report
💚

Waste Segregation & Composting

BDAHombale📞 Inbavalli AEE📞 Gunashekhar (Hombale)
5 tasks
  • Inbavalli AEE to provide per-block wet and dry waste bins
  • Install dry & wet waste bins across campus (Commissioner's proposal)
  • Inbavalli AEE to issue work order to Hombale for dedicated STP person
  • Inbavalli AEE to issue work order to Hombale for organic waste converter machine
  • Process wet waste through composting unit
💧

Basement Seepage

CivilBDACategory 1📞 Gunashekhar (Hombale)
2 tasks
  • Seal expansion joints opened by contractor during basement cleaning
  • Resolve ongoing water seepage in basement
🔋

DG Maintenance & Backup DG

Electrical⚠ Critical📞 Niranjan EE
2 tasks
  • Schedule and carry out DG maintenance
  • Arrange backup DG — critical during power failure
🔧

Transformer Maintenance

ElectricalBDA📞 Niranjan EE
2 tasks
  • Inspect transformers — power fluctuations reported in some flats
  • Address maintenance issues found
In Progress 19
🌧️

Rainwater Harvesting (RWH)

WaterBDACategory 1📞 Inbavalli AEE📞 Gunashekhar (Hombale)
9 tasks
  • 3 rainwater percolation pits unearthed using JCB from Hombale (8 Aug 2026)
  • Park-area pits surveyed — all located except 3 (16 Aug 2026 · Hombale survey team)
  • RWH survey maps received (16 Aug 2026)
  • Coordinated with NGO that constructed the pits (16 Aug 2026)
  • NGO heightening pits to current level using rings — target Wed 19 Aug 2026
  • Locate remaining 3 percolation pits in park area
  • Clean all rainwater harvesting tanks
  • Install motor/pump for RWH system
  • Connect percolation pits to RWH system

Earth Pits Maintenance

Electrical📞 Inbavalli AEE & Gunashekhar
3 tasks
  • 18 earth pits recovered
  • 8 more earth pits to go
  • JCB from Hombale deployed — also used to unearth 3 percolation pits
🧯

Fire Safety & Extinguisher Refill

Category 1⚠ Expires end of month📞 Inbavalli AEE
3 tasks
  • Fire extinguisher refill — expiring end of month, urgent
  • Fire alarm systems & fire safety equipment — pending
  • Inbavalli AEE to follow up
💦

Cauvery Water Connection

WaterBDACategory 1📞 Inbavalli AEE📞 Naveen AEE (BWSSB)🏆 Milestone
7 tasks
  • Formal request submitted by BDA to BWSSB (Dec 2025)
  • BWSSB agreed in principle — will issue demand note to BDA
  • EE Inbavalli & AEE Naveen visited Phase 2 (8 Aug 2026)
  • BDA confirmed will bear all expenses for all 3 phases
  • Larger-diameter BWSSB pipeline from Safal Market side
  • Demand note to be issued by BWSSB → BDA to process
  • BWSSB estimated timeline: 6 months to 1 year for completion
📄

KSPCB Consent Renewal

BDA📞 Inbavalli AEE
1 task
  • Show-cause notice — renewal in progress (Inbavalli AEE)
⚠️

STP Overhead Tank — Discolored Water

WaterCategory 1⚠ Health hazard📞 Inbavalli AEE📞 Niranjan EE📞 Gunashekhar (Hombale)
2 tasks
  • Complete motor installation with auto-controller to resolve discoloration
  • Hombale to assign dedicated STP maintenance person
🛑

Speed Breakers

CivilBDA📞 Niranjan EE
4 tasks
  • Locations and specs finalized
  • Speed breaker materials received (14 Aug 2026)
  • Stilt — speed breaker installation completed (21 Aug 2026)
  • Basement — speed breaker installation still pending
💧

Existing Borewells — 3 of 4 Failed

WaterCategory 1⚠ 3 failed📞 Inbavalli AEE📞 Gunashekhar (Hombale)
4 tasks
  • 1 existing borewell — motor repair completed, operational
  • Borewell near A block — failed, will not be restored
  • Borewell near B block — failed, will not be restored
  • Borewell in Labour Colony — failed, will not be restored
💧

New Borewells — 5 Drilled (2 Fitted, 2 Pending, 1 Failed)

WaterCategory 1📞 Inbavalli AEE📞 Gunashekhar (Hombale)
4 tasks
  • 2 new borewells — motors fitted, operational
  • 2 new borewells — motors yet to be fitted
  • 1 new borewell failed — no water found
  • Yield reports pending for all new borewells
⚙️

Fresh Water & STP Motors

WaterMaintenance📞 Niranjan EE📞 Gunashekhar (Hombale)
7 tasks
  • 14 new motors received in 2 batches
  • 7 Fresh Water motors — installed with starters
  • 7 STP motors — installed
  • 7 STP motor starters — scheduled Mon 17 Aug 2026
  • Contact automatic water controller team to verify post motor installation
  • Old 14 motors to STP building as backup
  • Coordination by Gunashekar Sir (Hombale) & BDA team
🤖

Water Automation Controller

WaterElectrical📞 Niranjan EE
4 tasks
  • Fresh water controller — installation in progress
  • Contact automatic water controller team to verify post motor installation
  • STP controller integrated
  • Generator made automatic
🔧

Plumbing & Blockages

WaterCivilCategory 1📞 Niranjan EE
4 tasks
  • Flat-by-flat checks — 70+ flats ongoing
  • External pipe access planning
  • Y-strainer installation — done for all 6 blocks (8×2.5" + 4×2" per block, 72 total)
  • Silt accumulation in pipes — ground sump filtration needed

Electrical Rectification

Electrical📞 Niranjan EE
8 tasks
  • E Block ATS — rectified by BESCOM & AXON
  • D Block ATS — rectified by BESCOM & AXON
  • MCB electrical issues in A, D & E Blocks — rectified
  • 3 street lights in front of B & C blocks — not working
  • Street lights towards F block and road — not working
  • Street lights near transformer — not working
  • Parking street lights — not working
  • Street lights towards back wall — not working
🏗️

Civil Works

Civil📞 Inbavalli AEE📞 Niranjan EE📞 Bhuvaneshwar EE📞 Jayaraj RCCL📞 Gunashekhar (Hombale)
8 tasks
  • Dust mound clearance — starts Mon 17 Aug, ~10 days (Bhuvaneshwar EE & RCCL DGM · target Wed 26 Aug)
  • Wall behind sump & STP — level with sand to stop water logging
  • Back wall — closed on transformer side with temporary sheets (not a permanent fix)
  • Back wall near STP — sped up, significant progress made
  • Back wall work started near F block
  • Inbavalli AEE & Niranjan EE to discuss with RCCL & Hombale for permanent resolution
  • Debris cleared
  • Slab replacement — not started yet
🌳

Park Work

CivilStarted Jul 16📞 Niranjan EE
5 tasks
  • Pavement laying — ongoing
  • Landscaping & debris removal — ongoing
  • Jogging track construction — commenced
  • Children's play area & walking track with gazebo — in progress, to be fenced
  • Remaining park works
🛡️

Security & CCTV

Security📞 Inbavalli AEE
6 tasks
  • Blind spots identified
  • 5 CCTV cameras installed
  • CCTV recording operational (NVR / HDD issue resolved)
  • Parking data consolidated
  • Boom barrier — requested for vehicle entry tracking
  • Parking allotment/numbering — flagged for discussion with BDA
💧

Water Complaints Resolution

WaterCategory 1📞 Inbavalli AEE
3 tasks
  • 161 flats tracked block-wise (A–F)
  • Plumbing team working through list
  • Staging-required flats being scheduled
📋

FMS & AMC

Maintenance📞 Niranjan EE📞 Niranjan EE
4 tasks
  • FMS EOI for empanelment submitted
  • Follow up with Niranjan EEAfter Aug 22
  • Motor AMC proposal
  • Define SOPs and accountability
Done 6
🤖

STP Controller & Generator Automation

ElectricalWater📞 Niranjan EE
2 tasks
  • STP automation controller integrated
  • Generator made fully automatic
♻️

STP Cleaning

WaterMaintenanceCategory 1👤 Person TBD📞 Gunashekhar (Hombale)
4 tasks
  • Sludge cleared
  • System cleaning completed
  • Motor servicing coordinated
  • Assign 1 person for ongoing STP monitoring
🛗

Lift Maintenance

Maintenance📞 Niranjan EE
7 tasks
  • Quarterly lift maintenance (6 July 2026) — done
  • B Block — 2 lifts done (passenger + service)
  • C Block — 2 lifts done (passenger + service)
  • D Block — 2 lifts done (passenger + service)
  • E Block — 2 lifts done (passenger + service)
  • F Block — 2 lifts done (passenger + service)
  • A Block — 2 lifts pending (passenger + service)
🧹

Basement & Stilt Cleaning

Civil📞 Gunashekhar (Hombale)
3 tasks
  • Basement cleaned
  • Stilt areas cleaned
  • Exit ramp blockage cleared
📱

MyGate & Documentation

Management
3 tasks
  • Vendor directory added
  • Parking data consolidated
  • Block SPOCs and issue tracking set up
📋

FMS EOI Submitted

Maintenance📞 Niranjan EE
1 task
  • Expression of Interest for FMS empanelment submitted