Status Tracker
Works taken up
Filter the dashboard to quickly see completed, ongoing and long-term items.
Borewells & Water Supply
Of 4 existing borewells, 1 working (motor repaired). Of 5 new borewells drilled, 2 motors fitted, 2 pending, 1 failed (no water).
Category 1📞 Inbavalli AEE📞 Gunashekhar (Hombale)
- ✓1 existing borewell — motor repair completed, operational
- ✕Borewell near A block — failed, will not be restored
- ✕Borewell near B block — failed, will not be restored
- ✕Borewell in Labour Colony — failed, will not be restored
- ✓5 new borewells drilled from the start
- ✓2 new borewells — motors fitted, operational
- ◑2 new borewells — motors yet to be fitted
- ✕1 new borewell failed — no water found
- ○Yield reports pending for all new borewells — follow up with Vinayak (Hombale)
Fresh Water & STP Motors
All 14 motors now installed and commissioned with starters — 7 Fresh Water + 7 STP motors.
📞 Niranjan EE📞 Gunashekhar (Hombale)
- ✓14 new motors received in 2 batches
- ✓7 Fresh Water motors — installed with starters
- ✓7 STP motors — installed
- ✓7 STP motor starters — installed 17 Aug 2026
- ○Contact automatic water controller team to verify system post motor installation
- ○Old 14 motors to be placed in STP building as backup for future use
- ✓Coordination by Gunashekar Sir (Hombale) & BDA team
Automation
Water controller installation in progress; STP and generator automation completed.
📞 Niranjan EE
- ◑Fresh water controller — installation in progress
- ○Contact automatic water controller team to verify system working post new motor installation
- ✓STP controller integrated
- ✓Generator made automatic
Plumbing & Blockages
180+ plumbing complaints fixed. Remaining 9 open cases are all on the 13th & 14th floors — escalated as a pressure-boosting design issue, not routine plumbing.
Category 1📞 Niranjan EE
- ✓Flat-by-flat checks — 180+ plumbing complaints fixed
- ◑Water pressure issues — 9 open cases, 100% on 13th & 14th floors: A-1303, A-1308, B-1302, D-1304, D-1406, D-1408, E-1406, E-1407, F-1406
- ◑External pipe access planning
- ✓Y-strainer installation — done for all 6 blocks (8×2.5" + 4×2" per block, 72 total)
- ○Silt accumulation in pipes — ground sump filtration solution needed
STP Cleaning
Critical cleaning and sludge-removal work completed.
Category 1👤 Person to be assigned📞 Gunashekhar (Hombale)
- ✓Sludge cleared
- ✓System cleaning completed
- ✓Motor servicing coordinated
- ○Assign 1 person for ongoing STP monitoring
Solid Waste Converter
Solid waste converter unit to be assigned and monitored.
Category 1👤 Person to be assigned📞 Gunashekhar (Hombale)
- ○Assign 1 person for solid waste converter
Locking Shaft & Missing Doors
List of locking shaft and missing doors being compiled from members.
Hombale📞 Gunashekhar (Hombale)
- ◑List of locking shaft & missing doors being compiled from members
- ○Gunashekhar (Hombale) to rectify broken/missing doors
Lift Maintenance
Full lift servicing had never happened before — SKRWA pushed for it and the first-ever full maintenance was carried out last month (July 2026) for B, C, D, E, F blocks. A Block's first full service is still pending.
📞 Niranjan EE
- ✓First-ever full lift maintenance carried out 6 July 2026
- ✓B Block — 2 lifts done (passenger + service)
- ✓C Block — 2 lifts done (passenger + service)
- ✓D Block — 2 lifts done (passenger + service)
- ✓E Block — 2 lifts done (passenger + service)
- ✓F Block — 2 lifts done (passenger + service)
- ◑A Block — 2 lifts pending (first-ever full service) — SKRWA following up with Niranjan EE
Electrical Rectification
ATS & MCB rectification complete for A, D & E blocks — BESCOM & AXON handled ATS repairs. All 9 street lights fixed; 1 pole near the back wall is down, pending the borewell motor fix nearby.
📞 Niranjan EE
- ✓E Block ATS (Automatic Transfer Switch) — rectified by BESCOM & AXON
- ✓D Block ATS — rectified by BESCOM & AXON
- ✓MCB electrical issues in A, D & E Blocks — rectified
- ✓Ranjith Electrical Contractor (BDA) — MCB follow-up completed
- ✓All 9 street lights fixed — B & C blocks, towards F block & road, near transformer & parking
- ◑1 street light pole near the back wall is down — to be fixed once the nearby borewell motor is fixed
Common Area Lighting (Block-wise)
A Block common-area lights fully fixed. SKRWA is consolidating faulty-light complaints and working with Hombale to rectify block by block; other blocks to follow.
📞 Gunashekhar (Hombale)
- ✓A Block — all common-area lights fixed
- ◑Complaints being consolidated block by block with Hombale
- ○B, C, D, E, F Blocks — to follow A Block's fix
Civil Works
Back wall near STP sped up. Dust mound clearance from Mon 17 Aug (~10 days). Wall behind sump & STP to be leveled with sand to stop water logging.
📞 Inbavalli AEE📞 Niranjan EE📞 Bhuvaneshwar EE📞 Jayaraj RCCL📞 Gunashekhar (Hombale)
- ◑Dust mound clearance — starts Mon 17 Aug 2026, ~10 days to complete Discussed with Bhuvaneshwar EE & RCCL DGM · target Wed 26 Aug 2026
- ◑Wall behind sump & STP — to be leveled with sand to stop water logging
- ◑Back wall — closed on transformer side with temporary sheets (not a permanent fix)
- ✓Back wall near STP — sped up, significant progress made
- ◑Back wall work started near F block
- ○Inbavalli AEE & Niranjan EE to discuss with RCCL & Hombale for permanent resolution
- ✓Debris removed
- ○Entry & exit slab replacement — following up with Gunashekhar sir (Hombale) for months, no visible update yet
Basement & Stilt Cleaning
Basement and stilt cleared; rear-side debris removal and recurring stilt debris cleanup now under active follow-up.
📞 Gunashekhar (Hombale)📞 RCCL
- ✓Basement cleaned
- ✓Stilt areas cleaned
- ✓Exit ramp blockage cleared
- ◑Rear-side debris removal (behind the apartment) — SKRWA following up with RCCL
- ◑Recurring stilt debris cleanup — follow-up ongoing with Hombale to keep stilt areas clear
Park Work
Park renovation ongoing since 16 Jul 2026. Percolation pit survey completed 16 Aug 2026 — 25 pits surveyed, 22 recovered & height-adjusted to the new park level, 3 not found.
📞 Niranjan EE
- ◑Pavement laying — ongoing
- ◑Landscaping & debris removal — ongoing
- ◑Jogging track construction — commenced
- ◑Children's play area & walking track with gazebo — in progress, to be fenced
- ○Remaining park works
Security & CCTV
5 CCTVs installed and recording is now operational. Tighter security protocols and regular patrolling now being implemented. Boom barrier and parking numbering remain pending.
Category 1📞 Inbavalli AEE📞 Gunashekhar (Hombale)
- ✓5 CCTV cameras installed
- ✓CCTV recording operational (NVR / HDD issue resolved)
- ✓Recording follow-up with Inbavalli AEE & Gunashekhar — completed
- ◑Tighter security implementation — gate protocols & visitor verification being strengthened, SKRWA following up
- ◑Patrolling implementation — regular campus/night patrol coverage being set up
- ○Boom barrier — requested for vehicle entry tracking
- ○Parking allotment/numbering — flagged for discussion with BDA
FMS & AMC
FMS EOI for empanelment submitted. Follow-up with Niranjan EE after 22 August.
📞 Niranjan EE
- ✓FMS EOI for empanelment submitted
- ○Follow up with Niranjan EEAfter Aug 22
- ○Motor AMC proposal
- ○Define SOPs and accountability
MyGate Block Admin & Documentation
Block Admin access enabled after Association registration; verification backlog being cleaned up and complaint tracking overhauled.
Category 1
- ✓Vendor directory added
- ✓Parking data consolidated
- ✓Block SPOCs and issue tracking set up
- ✓Block Admin access enabled on MyGate (previously never activated)
- ✓All complaints now tracked — every issue logged with a record instead of being lost in chat
- ✓Complaint consolidation — repeat/duplicate complaints across flats grouped to reveal patterns
- ✓Auto-assignment of issues to relevant departments (electrical, plumbing, civil, security)
- ◑Owner/tenant verification cleanup — clearing year-old pending approvals and unverified access grants
Resident Data-Collection Surveys
SKRWA has launched dedicated surveys via MyGate to systematically collect resident-reported issues across 4 categories, replacing scattered chat complaints.
Category 1
- ✓Survey created — hanging & non-working common-area lights
- ✓Survey created — blockage issues
- ✓Survey created — lift shaft issues
- ✓Survey created — housekeeping issues