Skandagiri Progress
Resident Progress Dashboard · April–July 2026

Three months of structured follow-up with BDA.

A transparent summary of infrastructure, water, electrical, lift, plumbing, civil and maintenance works taken up for Skandagiri Apartment through BDA, Hombale and service vendors.

Status Tracker

Works taken up

Filter the dashboard to quickly see completed, ongoing and long-term items.

💧
ONGOING

Borewells & Water Supply

Of 4 existing borewells, 1 working (motor repaired). Of 5 new borewells drilled, 2 motors fitted, 2 pending, 1 failed (no water).

Category 1📞 Inbavalli AEE📞 Gunashekhar (Hombale)
  • 1 existing borewell — motor repair completed, operational
  • Borewell near A block — failed, will not be restored
  • Borewell near B block — failed, will not be restored
  • Borewell in Labour Colony — failed, will not be restored
  • 5 new borewells drilled from the start
  • 2 new borewells — motors fitted, operational
  • 2 new borewells — motors yet to be fitted
  • 1 new borewell failed — no water found
  • Yield reports pending for all new borewells — follow up with Vinayak (Hombale)
⚙️
ONGOING

Fresh Water & STP Motors

All 14 motors now installed and commissioned with starters — 7 Fresh Water + 7 STP motors.

📞 Niranjan EE📞 Gunashekhar (Hombale)
  • 14 new motors received in 2 batches
  • 7 Fresh Water motors — installed with starters
  • 7 STP motors — installed
  • 7 STP motor starters — installed 17 Aug 2026
  • Contact automatic water controller team to verify system post motor installation
  • Old 14 motors to be placed in STP building as backup for future use
  • Coordination by Gunashekar Sir (Hombale) & BDA team

Automation

Water controller installation in progress; STP and generator automation completed.

📞 Niranjan EE
  • Fresh water controller — installation in progress
  • Contact automatic water controller team to verify system working post new motor installation
  • STP controller integrated
  • Generator made automatic
🔧
ONGOING

Plumbing & Blockages

180+ plumbing complaints fixed. Remaining 9 open cases are all on the 13th & 14th floors — escalated as a pressure-boosting design issue, not routine plumbing.

Category 1📞 Niranjan EE
  • Flat-by-flat checks — 180+ plumbing complaints fixed
  • Water pressure issues — 9 open cases, 100% on 13th & 14th floors: A-1303, A-1308, B-1302, D-1304, D-1406, D-1408, E-1406, E-1407, F-1406
  • External pipe access planning
  • Y-strainer installation — done for all 6 blocks (8×2.5" + 4×2" per block, 72 total)
  • Silt accumulation in pipes — ground sump filtration solution needed
♻️
COMPLETED

STP Cleaning

Critical cleaning and sludge-removal work completed.

Category 1👤 Person to be assigned📞 Gunashekhar (Hombale)
  • Sludge cleared
  • System cleaning completed
  • Motor servicing coordinated
  • Assign 1 person for ongoing STP monitoring
🧹
REQUESTED

Solid Waste Converter

Solid waste converter unit to be assigned and monitored.

Category 1👤 Person to be assigned📞 Gunashekhar (Hombale)
  • Assign 1 person for solid waste converter
🚪
ONGOING

Locking Shaft & Missing Doors

List of locking shaft and missing doors being compiled from members.

Hombale📞 Gunashekhar (Hombale)
  • List of locking shaft & missing doors being compiled from members
  • Gunashekhar (Hombale) to rectify broken/missing doors
🛗
ONGOING

Lift Maintenance

Full lift servicing had never happened before — SKRWA pushed for it and the first-ever full maintenance was carried out last month (July 2026) for B, C, D, E, F blocks. A Block's first full service is still pending.

📞 Niranjan EE
  • First-ever full lift maintenance carried out 6 July 2026
  • B Block — 2 lifts done (passenger + service)
  • C Block — 2 lifts done (passenger + service)
  • D Block — 2 lifts done (passenger + service)
  • E Block — 2 lifts done (passenger + service)
  • F Block — 2 lifts done (passenger + service)
  • A Block — 2 lifts pending (first-ever full service) — SKRWA following up with Niranjan EE
ONGOING

Electrical Rectification

ATS & MCB rectification complete for A, D & E blocks — BESCOM & AXON handled ATS repairs. All 9 street lights fixed; 1 pole near the back wall is down, pending the borewell motor fix nearby.

📞 Niranjan EE
  • E Block ATS (Automatic Transfer Switch) — rectified by BESCOM & AXON
  • D Block ATS — rectified by BESCOM & AXON
  • MCB electrical issues in A, D & E Blocks — rectified
  • Ranjith Electrical Contractor (BDA) — MCB follow-up completed
  • All 9 street lights fixed — B & C blocks, towards F block & road, near transformer & parking
  • 1 street light pole near the back wall is down — to be fixed once the nearby borewell motor is fixed
💡
ONGOING

Common Area Lighting (Block-wise)

A Block common-area lights fully fixed. SKRWA is consolidating faulty-light complaints and working with Hombale to rectify block by block; other blocks to follow.

📞 Gunashekhar (Hombale)
  • A Block — all common-area lights fixed
  • Complaints being consolidated block by block with Hombale
  • B, C, D, E, F Blocks — to follow A Block's fix
🏗️
ONGOING

Civil Works

Back wall near STP sped up. Dust mound clearance from Mon 17 Aug (~10 days). Wall behind sump & STP to be leveled with sand to stop water logging.

📞 Inbavalli AEE📞 Niranjan EE📞 Bhuvaneshwar EE📞 Jayaraj RCCL📞 Gunashekhar (Hombale)
  • Dust mound clearance — starts Mon 17 Aug 2026, ~10 days to complete Discussed with Bhuvaneshwar EE & RCCL DGM · target Wed 26 Aug 2026
  • Wall behind sump & STP — to be leveled with sand to stop water logging
  • Back wall — closed on transformer side with temporary sheets (not a permanent fix)
  • Back wall near STP — sped up, significant progress made
  • Back wall work started near F block
  • Inbavalli AEE & Niranjan EE to discuss with RCCL & Hombale for permanent resolution
  • Debris removed
  • Entry & exit slab replacement — following up with Gunashekhar sir (Hombale) for months, no visible update yet
🧹
ONGOING

Basement & Stilt Cleaning

Basement and stilt cleared; rear-side debris removal and recurring stilt debris cleanup now under active follow-up.

📞 Gunashekhar (Hombale)📞 RCCL
  • Basement cleaned
  • Stilt areas cleaned
  • Exit ramp blockage cleared
  • Rear-side debris removal (behind the apartment) — SKRWA following up with RCCL
  • Recurring stilt debris cleanup — follow-up ongoing with Hombale to keep stilt areas clear
🌳
ONGOING

Park Work

Park renovation ongoing since 16 Jul 2026. Percolation pit survey completed 16 Aug 2026 — 25 pits surveyed, 22 recovered & height-adjusted to the new park level, 3 not found.

📞 Niranjan EE
  • Pavement laying — ongoing
  • Landscaping & debris removal — ongoing
  • Jogging track construction — commenced
  • Children's play area & walking track with gazebo — in progress, to be fenced
  • Remaining park works
🛡️
ONGOING

Security & CCTV

5 CCTVs installed and recording is now operational. Tighter security protocols and regular patrolling now being implemented. Boom barrier and parking numbering remain pending.

Category 1📞 Inbavalli AEE📞 Gunashekhar (Hombale)
  • 5 CCTV cameras installed
  • CCTV recording operational (NVR / HDD issue resolved)
  • Recording follow-up with Inbavalli AEE & Gunashekhar — completed
  • Tighter security implementation — gate protocols & visitor verification being strengthened, SKRWA following up
  • Patrolling implementation — regular campus/night patrol coverage being set up
  • Boom barrier — requested for vehicle entry tracking
  • Parking allotment/numbering — flagged for discussion with BDA
📋
ONGOING

FMS & AMC

FMS EOI for empanelment submitted. Follow-up with Niranjan EE after 22 August.

📞 Niranjan EE
  • FMS EOI for empanelment submitted
  • Follow up with Niranjan EEAfter Aug 22
  • Motor AMC proposal
  • Define SOPs and accountability
📱
ONGOING

MyGate Block Admin & Documentation

Block Admin access enabled after Association registration; verification backlog being cleaned up and complaint tracking overhauled.

Category 1
  • Vendor directory added
  • Parking data consolidated
  • Block SPOCs and issue tracking set up
  • Block Admin access enabled on MyGate (previously never activated)
  • All complaints now tracked — every issue logged with a record instead of being lost in chat
  • Complaint consolidation — repeat/duplicate complaints across flats grouped to reveal patterns
  • Auto-assignment of issues to relevant departments (electrical, plumbing, civil, security)
  • Owner/tenant verification cleanup — clearing year-old pending approvals and unverified access grants
📝
ONGOING

Resident Data-Collection Surveys

SKRWA has launched dedicated surveys via MyGate to systematically collect resident-reported issues across 4 categories, replacing scattered chat complaints.

Category 1
  • Survey created — hanging & non-working common-area lights
  • Survey created — blockage issues
  • Survey created — lift shaft issues
  • Survey created — housekeeping issues
Pending Requests

Raised with BDA & Hombale

Work items formally requested but not yet actioned. Click any card to expand details.

💚
REQUESTED

Waste Segregation & Composting

Dry/wet bins and organic composting unit — as proposed by Commissioner Sir.

📞 Inbavalli AEE📞 Gunashekhar (Hombale)
  • Inbavalli AEE to provide per-block wet and dry waste bins
  • Install dry and wet waste segregation bins across campus
  • Inbavalli AEE to issue work order to Hombale for dedicated STP person
  • Inbavalli AEE to issue work order to Hombale for organic waste converter machine
  • Process wet waste through composting unit
🌧️
ONGOING

Rainwater Harvesting (RWH)

Park-area percolation pits: 25 surveyed on 16 Aug 2026 — 22 recovered, working, and height-adjusted to the new park level; 3 could not be located.

Category 1📞 Inbavalli AEE📞 Gunashekhar (Hombale)
  • 3 rainwater percolation pits unearthed using JCB from Hombale 8 Aug 2026
  • 25 park-area percolation pits surveyed — 22 recovered & working, 3 not found 16 Aug 2026 · Hombale survey team
  • RWH survey maps received 16 Aug 2026
  • Coordinated with NGO that originally constructed the percolation pits 16 Aug 2026
  • NGO heightened 22 recovered pits to current ground level using rings
  • 3 percolation pits could not be located
  • Clean all rainwater harvesting tanks
  • Install motor/pump for RWH system
  • Connect percolation pits to RWH system
💧
ONGOING

Basement Seepage

Water seepage through expansion joints opened during basement cleaning — SKRWA actively following up with BDA for sealing.

Category 1📞 Inbavalli AEE (BDA)
  • Seal expansion joints in basement (opened by contractor) — SKRWA following up with BDA
  • Resolve ongoing water seepage in basement — SKRWA following up with BDA
🛑
COMPLETED

Speed Breakers

20+ speed breakers installation completed — stilt completed 21 Aug 2026, basement now completed too.

📞 Niranjan EE
  • Locations and specs finalized
  • Speed breaker materials received 14 Aug 2026
  • Stilt — speed breaker installation completed 21 Aug 2026
  • 20+ speed breakers installation completed across stilt & basement
ONGOING

Earth Pits Maintenance

18 of 26 earth pits recovered; 8 more to go. JCB from Hombale deployed.

📞 Inbavalli AEE📞 Gunashekhar (Hombale)
  • 18 earth pits recovered
  • 8 more earth pits to go
  • JCB from Hombale deployed — also used to unearth 3 rainwater percolation pits
🔋
REQUESTED

DG Maintenance & Backup DG

Critical during power failure. Current DG maintenance and backup DG required.

📞 Niranjan EE
  • DG maintenance — schedule and carry out
  • Arrange backup DG for critical power failure cover
🔧
REQUESTED

Transformer Maintenance

Recent power fluctuations in some flats. Transformers to be inspected and serviced.

📞 Niranjan EE
  • Inspect transformers — check for maintenance issues
  • Address power fluctuation cause in affected flats
💦
MILESTONE

Cauvery Water Connection

BWSSB agreed in principle. EE Inbavalli (BDA) & AEE Naveen (BWSSB) visited Phase 2 today. Demand note to be issued shortly.

Category 1📞 Inbavalli AEE📞 Naveen AEE (BWSSB)
  • Formal request submitted by BDA to BWSSB (Dec 2025)
  • BWSSB agreed in principle — will issue demand note to BDA
  • EE Inbavalli & AEE Naveen visited Phase 2 for site review (8 Aug 2026)
  • BDA confirmed will bear all expenses for all 3 phases (security deposit, civil works, installation)
  • Larger-diameter BWSSB pipeline to be laid from Safal Market side
  • Demand note to be issued by BWSSB → BDA to process payment
  • BWSSB estimated timeline: 6 months to 1 year for completion
📄
ONGOING

KSPCB Consent Renewal

Show-cause notice from KSPCB to renew department's consent within 45 days of expiry.

📞 Inbavalli AEE
  • Renewal in progress (Inbavalli AEE)
⚠️
ONGOING

STP Overhead Tank — Discolored Water

Health hazard flagged: tank not refilling before fully depleting, causing sediment to reach flats since motors aren't installed with auto-controller yet.

Category 1📞 Inbavalli AEE📞 Niranjan EE📞 Gunashekhar (Hombale)
  • Complete motor installation with auto-controller to resolve discoloration
  • Hombale to assign dedicated STP maintenance person (health hazard)
🧯
ONGOING

Fire Safety & Fire Extinguisher Refill

Fire extinguisher refill expiring end of this month — urgent renewal required. Fire alarm systems and fire safety equipment also pending.

Category 1⚠ Expires end of month📞 Inbavalli AEE
  • Fire extinguisher refill — expiring end of month, urgent
  • Fire alarm systems & fire safety equipment — pending
  • Inbavalli AEE to follow up
🚿
REQUESTED

Exit Valve — Fresh Water Connections

Exit valve pending for all fresh water connections, including 13th & 14th floor extension.

Category 1📞 Niranjan EE
  • Install exit valve for 13th & 14th floor extension
  • Install exit valve for all fresh water connections
Resident Complaints Tracker

Water complaints — block-wise

161 unique flats have logged water complaints across blocks A–F. Tracked flat-by-flat with live status — 9 open on floors 13 & 14 (low pressure).

22Block A
34Block B
22Block C
32Block D
28Block E
23Block F
161Total flats (A–F)
New / Open
Complaints logged but not yet acted on — need plumbing team visit.
Staging Required
External pipe access needed — scheduled for next round of works.
Resolved
Visited, issue addressed and closed by the plumbing team.
View Full Water Complaints Tracker →
Block Coverage

A–F block coordination

Lift, electrical, plumbing, water and common-area issues have been tracked block by block.

AWater, MCB, common works
BWater, lifts, common works
CLift bulbs, PCB, water
DMCB, lifts, water
EPlumbing, MCB, lift
FSecurity, parking, lifts
Progress Timeline

How the work moved

Work doneElectrical

All 9 street lights fixed

All street lights across B & C blocks, towards F block & road, near transformer & parking are now fixed. One pole near the back wall remains down, pending the nearby borewell motor fix.

Work doneDocumentation

4 resident surveys launched via MyGate

SKRWA created dedicated surveys to systematically collect data on hanging/non-working common-area lights, blockage issues, lift shaft issues, and housekeeping issues.

Work doneDocumentation

MyGate Block Admin access enabled

After Association registration, Block Admin access was activated for the first time. All complaints are now tracked, consolidated to reveal repeat/duplicate patterns, and auto-assigned to the relevant department, with owner/tenant verification cleanup ongoing.

Work doneElectrical

A Block common-area lights fixed

All common-area lighting issues in A Block are resolved. SKRWA is now consolidating complaints and working with Hombale to rectify the remaining blocks one at a time.

In progressCivil · Lifts · Security

SKRWA opens 6 new follow-ups

Rear-side debris removal, recurring stilt debris cleanup, basement seepage sealing, full lift servicing (beyond annual maintenance), tighter security protocols, and campus patrolling implementation are now being actively followed up with BDA/Hombale.

Work doneCivil

20+ speed breakers installed

Basement speed breaker installation is now complete, joining the stilt installation finished on 21 Aug. 20+ speed breakers are installed in total across stilt & basement — the item is fully closed.

Work doneWater

All 14 motors installed with new starters

The remaining 7 STP motor starters are now installed, completing all 14 motors (7 Fresh Water + 7 STP) with starters.

Work doneWater

Plumbing & blockages fixed across 180+ complaints

All previously flagged blockage cases were resolved; only water pressure issues on the 13th & 14th floors remain outstanding.

Work donePark

Park-area percolation pits recovered and leveled

Of 25 percolation pits surveyed in the park area, 22 were recovered, found working, and height-adjusted to the new park level by the NGO; 3 could not be located.

In progressCivil

Speed breakers — stilt completed, basement pending

Speed breaker installation on the stilt completed. Installation in the basement is still pending — follow up with Niranjan EE.

Follow-up doneWater

BWSSB Kaveri connection — major milestone

EE Inbavalli (BDA) & AEE Naveen (BWSSB) visited Phase 2. BWSSB agreed in principle to provide a dedicated Kaveri connection. BDA confirmed it will bear all expenses for all 3 phases. Larger-diameter pipeline from Safal Market side planned.

Follow-up doneWater · Civil

Motors, speed breakers & dust clearance — schedule confirmed

Speed breaker materials received 14 Aug; installation from Mon 17 Aug. Remaining 7 STP motor starters scheduled Mon 17 Aug — all 14 motors (7 fresh water + 7 STP) with starters. Automatic water controller team to verify post-installation; old 14 motors to STP building as backup. Dust mound clearance agreed with Bhuvaneshwar EE & RCCL DGM — starts Mon 17 Aug, ~10 days (target Wed 26 Aug). Wall behind sump & STP to be leveled with sand to stop water logging.

Work doneWater · Park

Park percolation pits surveyed — maps received

Hombale survey team located all park-area percolation pits except 3. Survey maps received and coordination completed with the NGO that originally built the pits. NGO to raise pit height to current ground level using rings by Wed 19 Aug 2026.

Work doneWater

JCB from Hombale unearthed 3 rainwater percolation pits

JCB obtained from Gunashekhar (Hombale) and deployed on campus. Three percolation pits for rainwater harvesting were unearthed.

Follow-up doneBESCOM

Gruha Jyothi re-verification held

A second on-campus verification window was coordinated for residents who missed the earlier session.

Work doneElectrical

D and E Block ATS issues rectified

Automatic power-changeover faults in both blocks were confirmed complete after follow-up with BDA and Hombale.

In progressWater

Fourteen new water motors received

Four motors were commissioned, eight more arrived, and two defective units entered warranty replacement.

Follow-up doneMaintenance

BDA released the FMS empanelment EOI

The resident-backed request progressed to BDA's formal vendor-empanelment stage.

In progressPark

Park renovation moved into execution

Pavement laying started as the first visible phase of the approved park work.

Work doneElectrical

ATS repairs completed by BESCOM & AXON

D and E Block Automatic Transfer Switch repairs completed by BESCOM and AXON teams.

Work doneCivil

Back wall near STP sped up

Construction of the back wall near the STP has been accelerated with significant progress made.

Follow-up pendingCivil

Back-wall completion escalated

The open stretch near F Block was raised for closure while the permanent boundary work remained pending.

In progressWater

New motor installation started

Sump levels were managed so the installation team could fit and commission the new motors safely.

Work doneCivil

Damaged entry and exit slabs repaired

The basement access slabs were restored for vehicle movement; other broken slabs remained under follow-up.

Follow-up doneWater

Long-term motor replacement plan agreed

BDA, Hombale, and the vendor aligned on procuring fourteen motors instead of continuing repeated short-term repairs.

In progressCivil

Boundary work advanced to the next contractor

Hombale completed its portion and RCCL began the next stage of the back-wall work.

Work doneDocumentation

Parking data added to MyGate

BDA parking allocations were consolidated so residents could verify slots and improve vehicle tracking.

Work doneLifts

All lift shafts cleaned

The cleaning reduced infrastructure risk and monthly lift maintenance was scheduled from July.

Work doneWater

Four borewells made operational

All four commissioned borewells were reported running with 7.5 HP motors.

In progressAutomation

Fresh-water controller installed

Controllers and level sensors were installed across all blocks and moved into testing and calibration.

Work doneWater

New borewell connections completed

Newly drilled borewells were connected into the apartment water system.

Work doneCivil

Exit-ramp drainage and borewell protection completed

The exit drain was cleaned, leaking pipes were clamped, and the outside borewell received vehicle protection.

In progressInfrastructure

Water-controller and CCTV installation commenced

Both long-pending systems moved from follow-up into on-site execution.

Work doneWater

External borewell connected to the tanks

The roadside borewell motor was switched on and water delivery to the apartment tanks was confirmed.

Follow-up pendingMaintenance

FMS consent collection opened

An owner-signature request was placed at security to support BDA's private FMS empanelment process.

Work doneElectrical

C Block common-area lights restored

The common-area lighting was switched back on after follow-up.

In progressCleaning

Basement debris removal started

The cleanup began in F and E Blocks and continued through the remaining basement areas.

Follow-up pendingWater

Overdue roadside borewell motor escalated

The month-long motor delay was raised again for action.

Follow-up doneCoordination

Pending-work deadlines secured at BDA Open House

Water, STP, automation, CCTV, lifts, civil works, and security items received named follow-up dates.

Follow-up doneCoordination

BDA commitments documented

A commissioner-level meeting recorded security restoration and deadlines for major pending works.

Transparent follow-up. Documented progress.

This dashboard is ready to be updated as new works are completed and can serve as a public record for residents and future committees.